Management of Construction Contracts
Evaluation Processes
By Gursharan Singh C.M.I.I.A.
1.0 Introduction
1.1 The successful implementation of any
Construction Contract, prior to commencement of any actual construction, is
dependent on four main components. These are:
[a] Owner’s/Client’s Financial and
Managerial In-House Resources;
[b] Technical Professionals Engaged to
Design and Supervise the Project;
[If appointed in the absence of
In-House expertise or relevant expertise]
[c] Contractors to Implement the Contract;
and
[d] Tenders/Bids Submitted for construction.
1.2 Thus it is important that the Client
evaluates the above four components prior to the commencement of any
construction works. There are several other aspects that contribute to the
successful completion but these are not the subject of this article.
2.0 Objectives
2.1 The general objective of the evaluation
is to
[a] Create awareness of the importance of
the various conditions that should be complied
[b] Identify and avoid any
weaknesses/shortcomings that may have financial implications & fraudulent
opportunities/possibilities; and
[c] Institute promptly any appropriate and
necessary remedial measures for any identified weaknesses/shortcomings by
the respective level of Management.
2.2 The specific objective of the
evaluations of the above referred four individual components is to ensure
that they have the required expertise and resources to ensure the successful
completion of the works in a cost-efficient and cost-effective manner.
3.0 Evaluations
Tender Evaluation Committee – ‘TEC’
3.1 Evaluations should be performed by a
committee that should be composed of individuals who are independent,
without any possibility of conflict of interest and with the relevant
expertise. The representative departments should include, in addition to
others that may be relevant, the following:
[i]
Project/Contract Department [In-House/Appointed Private - Technical
Professionals]
[ii] Finance Department
[iii] Another Department [such as Legal,
Company Secretary]
A Non-Executive Independent Director of the
Board of Directors [BOD] should chair the TEC where the value of the
contract exceeds a certain value as may have been prescribed in the
Discretionary Authority Limits [DAL] as prescribed by the BOD.
3.2 There can be several TECs for contracts
of different levels of financial commitment but their composition and the
limits should be as approved by the BOD.
Aspects for Evaluation
3.3 Detailed below are the aspects that need
to be evaluated for each of the above four components.
A – Client
[a] Client should undertake an In-House
Evaluation of its own ability to ensure the successful completion of the
‘Works’. Arrangements should be made
for an in-depth study of the proposed contract vis-à-vis its own ability to
implement and supervise/monitor the contract before approval and committing
the necessary financial resources. The aspects of the study can be listed
in a ‘Management Paper’ for prior approval of the In-House relevant
authorities [Board of Owners/Directors]. The contents of the ‘Management
Paper’ should include, among others, the following:
[i] Justification –
Cost-Effective;
[ii] Source & Cost of
Financing;
[iii] Scope of Works vis-à-vis
Approved Budget;
[iv] Method of Implementation;
[v] Supervision and Monitoring
[vi] Bid Invitation Procedures;
[vii] Terms & Conditions
including any Special Conditions;
[viii] Letter of Award
[Acceptance] and Formal Contract Documents [DAL]; and
[ix] Financial Viability Study
Report [Commercial Projects]
B – Technical Processionals
[a] The selection of private ‘Technical
Professionals’ should be evaluated to ensure that the appointed
‘Consultants’ will be able to provide quality services. The appointment
should be based on aspects that may include the following:
[i] Registration with the relevant
Regulatory Authorities
[Boards of Architects, Engineers,
Quantity/Land Surveyors]
[ii] Relevant Expertise vis-à-vis Project
to be designed and implemented
[iii] Resources – Expertise, Manpower,
Logistics & Finances
[iv] Past Experience – Relevant to the
Project
[v] Performance of past projects
[vi] Existing Projects in Hand – Work Load
including location of the projects
[vii] Public Relations status with other
parties – Authorities, Contractors, etc.
C – Contractors
[a] The evaluation of the contractors should
be based on aspects that should include, among any others that may be deemed
appropriate by Management, the following:
[i] Registration with any prescribed
relevant statutory authority and any in-house prescribed registration;
[ii] Organization - Management Structure;
[iii] Financial Status together with
Published Financial Statements & Annual Reports;
[iv] Relevant Expertise - Technical
Management & Skilled Manpower;
[v] Logistical Resources -
Plant/Machinery/Equipment [Owned and Available];
[vi] Experience - Completed Project with
current status of those completed projects;
[vii] Current Contracts - In Progress,
Status and Location;
[Separate listing for projects in
overseas locations]
[viii] Public Relations status with
statutory authorities, sub-contractors, suppliers, others;
D – Tenders/Bids
Responsibility of TEC
[a] Evaluation of bids to be limited to the
those bids received from contractors who have been evaluated as capable and
thus short listed. The minimum number of bids to be evaluated should be
three and maximum should be five. However, in the event there are more bids
that are within, say, a five percent margin of the in-house estimate then
the number to be evaluated can be increased.
[b] However, in the event the margin of
difference is substantially higher than the five percent margin for bid of
value lower than the in-house estimate, these low priced bids should also be
evaluated to ascertain the reasons for the substantial low bid. Any
substantiated justification should be taken into account in grading the
contractors.
[c] The responsibilities of the TEC include
the following:
[i] Bids provide the following details:
- Name of Contractors with relevant
registration and grading; and
- Bid Value and proposed Completion Period
Note: All developed countries and many
developing countries have established ‘Agencies/Authorities’ with the
primary objective of enhancing the performance of the construction industry
through the institution of several measures. These measures include doing
planning and research, providing statistical data, ensuring the adequate
supply of building materials and labor, streamlining the laws to be industry
friendly and provide assistance/incentives as appropriate. Another important
function is to assist/provide/expand the facilities to increase/upgrade the
skills that are relevant to the construction industry. It may be mandatory
that the contractors to be evaluated are registered with the prescribed
‘Agency’ with appropriate ‘Class/Category’ and ‘Expertise’. Most large
specialized corporations generally evaluate prospective contractors and it
is mandatory that be registered with them. These would include companies in
specialized business such as oil, telecoms, power generation, etc.
Evaluation Criteria - Bids
[a] The criteria for evaluation of
tenders/bids should include the below listed main aspects, among others
deemed appropriate and relevant to the scope of works, that should be
complied. It should be done only for the short listed bids. The main aspects
would include:
[i] The Bids are complete, without any
amendments, corrections, alternatives, unless requested, and in strict
compliance of all prescribed requirements. This is to ensure that a legally
binding Letter of Award can be issued for the accepted bid.
[ii] All contractors have complied with the
prescribed financial Guarantees/Bonds/Deposits in the prescribed formats and
approved financial institutions. [References/Copies to be attached for
verification]
[iii] Total bid sum is within the prescribed
margins of the in-house estimated sum.
Note: The in-house estimate should be
prepared in duplicate. It should be prepared preferably by a single
professional and checked by a qualified technical professional [quantity
surveyor for ‘building’ contracts or engineer for ‘infrastructure’
contracts] and finalized at least two weeks prior to the advertised closing
date of acceptance of bids. It should be certified by the responsible
professional and the head of the technical department. A copy of the
in-house estimate should be placed in the ‘tender box’ before the advertised
closing date with the second copy to marked ‘confidential’ and retained by
the relevant head of department.
[iv] The individual items are priced
reasonably and comparable to in-house rates. The evaluation should include
proposed ‘Rationalization’ of contractor’s individual rates that are not in
line with the in-house estimated individual rates vis-à-vis individual
quantities of scope of works.
[v] Pricing of individual sections and items
is in tandem with prescribed methods that are detailed in the tender
documents. Any variance may result in rejection of the bid.
[vi] Computation errors are listed and
quantified with its effect on the overall bid value.
[vii] The completion period is in line with
the in-house pre-determined period. In the event of any variances of this
period the evaluation should provide the financial implications of the
difference in period.
[viii] The evaluation process should be
completed well in advance within the Tender Validity Period [TVP]
that should be reasonable in duration and forward its recommendations to the
appropriate approving authority or BOD to enable it to arrive at a decision
for a Letter of Award/Acceptance [LOA] to be issued before the expiry
of the TVP to the successful contractor.
Technical Evaluation
3.4 Mega engineering projects are generally
implemented under a system known as the ‘Two Envelope System’. In this case
the proposals are received under two separate sealed envelopes. The
‘Financial Evaluation’ is done for all contracts and recommendations made.
The Technical Proposals submitted by at least three contractors whose bids
are recommended under the ‘Financial Evaluation’ are then opened and
evaluated. The financial implications of the two evaluations are then
compared. The bid that has the best combined acceptability is then
recommended to the BOD. The TEC for ‘Technical Evaluation’ is composed of
Technical Professionals with the relevant expertise.
Bids Received after the Closing Time
3.5 Bids ‘Received Late’ should be opened
and evaluated only in the event when none of the evaluated bids are
acceptable for whatever reason. However, this should be done with the prior
approval of the BOD giving full particulars of the circumstances. Bids
should not be rejected if the delay is due to any substantiated ‘technical’
reasons. An example of a ‘technical’ reason could be a last minute
declaration of holiday of the ‘closing date’ for submission of tenders.
4.0 Recommended Bid
4.1 The recommended bid should be
accompanied with the following schedules together with clear photostat
copies of any attachments, indexed and forwarded to the BOD or its appointed
Sub-Committee for scrutiny and forwarded to the BOD or other approved
authority for approval.
[a] Copy of Tender Advertisement or other
means of short listing/restricting of contractors with approval of the BOD
for such method of invitation of bids.
[b] List of Bids received as listed by the
TOC together with the unopened bids that were received after the tender
closing time.
[c] List of Bids in escalating order of
costs beginning with the lowest bid and rising to the highest cost.
[d] List of Clarifications enquiries
received and replies given and distributed to all contractors.
4.2 It is important that the recommendations
of the TEC are accompanied with, among others, basis/criteria used and
evaluation methodology including of the two envelope systems where
applicable.
5.0 CONCLUSION
5.1 It is a trend among professionals to
give weight to the various aspects in preparing their evaluation reports of
the received bids or have a ‘Score Card’. However this system is very
subjective and susceptible to easy manipulation that can give rise to
fraudulent opportunities and possibilities. Thus it would be in Managements
interest to be aware of the risks of the weight system before giving any
importance to the ‘Score Card’ system and using it in its selection
decision.
5.2 The above notes have been prepared in a
manner where the above notes are easily understood by BOD/Senior Management
whose members are generally non-technical professionals. They are based on
personal practical experiences during audit of the many construction
contracts/projects during the past [37] years of audit. It was observed
during those audits that generally there were many aspects that could not
have been understood by non-technical Senior Management Executives/BOD and
thus it may not have been possible for them to ascertain whether the
recommendations contributed to the quality of the evaluation reports or
achieved the required objective of cost-efficiency and cost-effectiveness in
the implementation of the contract. Approvals may have been given by BOD for
bid/tender acceptance based on recommendations of technical professionals
based on trust [blind trust] in their views.
5.3 It should be noted that each
professional has his/her own views regarding the degree of importance that
should be attached to the various aspects/components/methodologies that
contribute to a ‘Bid Evaluation’. Thus it is possible that there would be
other professionals whose views may differ from those provided above and
they are respected.
Irrelevant Information in any
Evaluation Report does not contribute to
Cost-Efficiency and Cost-Effectiveness.
Quantity only Increases Confusion
GSK/Apr
05
Note: The writer welcomes any
comments/enquiries from readers with a view to enhance and share knowledge.
Thank you.
-
GURSHARAN SINGH C.M.I.I.A.
[Trainer – Retired Audit Officer]
116 Jln Hujan Manik O.U.G. Jln Kelang 58200 Kuala Lumpur, Malaysia
[Tel, No. [H] 603-79824492 E-mail: gsk38@hotmail.com;
sharwant38@yahoo.com
-
- The opinions, beliefs and viewpoints expressed by
the various authors and forum participants on this web site do not
necessarily reflect the opinions, beliefs and viewpoints of AuditNet®
|