
Squandering Capital – Is the party REALLY over?
By Al M. Gray
With returns of several multiples of its costs, Construction Auditing has
succeeded in capturing the attention of the auditing profession. However,
there is the danger that success in controlling costs from outside
contractors is not met with equal vigor in a sustained emphasis on sound
internal controls over capital spending.
Loose Controls are the Norm
The
reasons are legion. Introspection is unpleasant. Senior management is
disinterested because capital projects are not a core business activity.
Boards of Directors bless projects, and then essentially go away. A truly
disciplined set of capital spending controls eliminates considerable
flexibility, as well as temptation at all levels of management, to
bury operating expenses as capital expenditures. The combination of these
factors produces forces that squander capital at a far more prodigious rate
than can be forestalled by construction auditing. Conversely, the financial
rewards from sound internal controls from conception to completion of all
capital projects dwarf those from construction auditing.
Undoubtedly the corporate accountability and oversight reforms necessitated
by the accounting scandals of recent years will produce changes in the realm
of capital spending. Beyond the well-publicized fraud at Worldcom Inc.,
where operating expenses were improperly reclassified as capital
expenditures, elements of capital spending fraud were also alleged at Rite
Aid, Adelphia, and Astra. Corporations have also experienced outbreaks of
fraud in capital projects at every level of management. Changes will come,
but will they result in implementation of rudimentary controls geared to
absolve managers and boards of liability or comprehensive ones that maximize
returns on capital spending projects? Which will your organization opt for?
A
few organizations and corporations are very frugal with appropriations of
capital and have implemented tough standards designed to preserve capital
and maximize project returns. These entities have a competitive advantage
over their peers stemming from more productive use of capital.
What are the most valuable practices of these organizations? At the core
level they include: appropriation, scope, cost, design, and close-out
controls. At the precision level they include engineering, estimating,
accounting, tax, legal, transportation, operational process, training,
safety, risk management, and procurement controls. Each of these deserves
separate discussion and analysis, once an organization chooses to evaluate
and implement a comprehensive controls set.
The Scope Deletion Dodge
Doing justice to a topic so complex and important is difficult, so let’s
consider one of the primary deficiencies encountered with capital
appropriations policies and procedures: Many do not require approval
for scope deletions or reductions.
The
amount of detail that can be brought to the board level is limited.
Organizations compensate for this by only bringing capital spending projects
to their boards for approval, with no requirement that the board approve
deductive changes. Some go so far as to allow cost overruns of ten or
fifteen percent without board approval in the form of an appropriation
change. The combination leaves management with broad capability to
misrepresent project results. Projects that were actually 30% over budget on
the approved scope of work may never receive board attention because
management deleted a portion of the approved scope concurrently with
incurring an eight or nine percent overrun.
Let’s use a fictional project to illustrate these concepts. (The story is a
composite of actual cases, with names, places, project type and numbers
changed. Any resemblance to any real project is both coincidental and
unintended.)
The project was “under budget” – the CEO said so!
“Tonight on Cashline, Hugh interviews Proudico CEO Rolle Player, who has
engineered a dramatic turnaround in the fortunes of this Fortune 50
manufacturer,”
Upon hearing these words the auditor grabbed his dinner plate from the table
and moved into the den to hear the interview with this familiar,
highly-regarded CEO.
The
interview began. After the usual discussion of Proudico’s financial
performance, soaring share price, and rumored acquisitions, Hugh Hobbs
turned to the corporation’s growth. “Rolle what areas of growth do you
anticipate for Proudico over the next two years?” Rolle Player leaned
forward in his chair, then said with a straight face “We anticipate the
growth in fireworks papers to explode from the wave of patriotism sweeping
the country. Our company just completed a $100 million expansion of its Zany
mill to include new production machinery to service this market. The project
was completed on time and under budget.”
The
auditor nearly choked upon hearing the last comment, before erupting with
laughter. His wife came running in to see what was going on. She exclaimed
“What is SO funny about a business news show?” The auditor responded “Honey,
its one of those auditing things you would not understand. Please excuse the
dinner interruption. The chicken casserole was wonderful tonight….” With
that he turned the television off and rejoined the family at the dinner
table, glad that his cooking duties were over before the show, so the
muffins were not in their usual charred state – unlike Proudico’s capital
budget.
What the auditor found amusing, yet disturbing, was that the CEO had uttered
astoundingly misleading comments to a national television audience, yet the
source of the deceit was allowed and condoned by the company’s capital
appropriation process. How? The CEO had taken advantage of the Scope
Deletion Dodge that is in wide acceptance among corporations and
organizations. This trick allows management, nearly always at every level,
to mislead shareholders, directors, and even senior management themselves
about project costs. Worse, when this dodge is accepted and condoned, it
provides opportunities for massive fraud. Finally, it puts the corporation
at a competitive disadvantage to peers who are more vigilant in spending
capital.
The Scope Deletion Game
Let’s review how this gimmick works.
In
reality, the Zany mill project was $28 million OVER BUDGET on the scope of
work as approved by the Board of Directors. While it was true that the final
project costs of $108 million were under the 10% overrun threshold that
would have necessitated approval of board approval of an appropriation
change, there were several deductive changes to the project scope that
reduced the capacity and future expandability of the plant from the levels
approved and funded by the board.
The
original project included a line item for a new gas turbine generator at a
budgeted cost of $15 Million. This equipment as not purchased and installed
under the main plant appropriation. The funds for the equipment were
re-appropriated under a separate authorization, without a corresponding
reduction in the budget for the main plant. For this item the unrecorded
budget reduction was $15 million, leaving an adjusted project budget of $85
million.
The
original project included a line item for $5 million in major spare parts
within the detailed project budget, which supported the appropriation
request approved by the Board of Directors. Very few spares were purchased,
due to cost overruns in other areas of the project. For this item the
unrecorded budget reduction was $4 million, leaving an adjusted project
budget of $81 million.
The
main appropriation also contained funding for training. All training costs
were charged to operating expense accounts, due to the lack of remaining
funds as the project neared completion.
For
this item the unrecorded budget reduction was $1 million, leaving an
adjusted project budget of $80 million.
Had
the original appropriation been adjusted for all of these scope reductions,
the approved budget would have been $80 million. With final reported project
costs of $108 million the ACTUAL cost overrun was $28 million. Final cost
exceeded appropriated costs by 35%, yet the CEO could state with his notion
of validity, that the project was “completed within budget.”
How?
Under the policies and procedures adopted for the corporation, there was no
requirement for an appropriation change when the scope of an approved
project was reduced, creating nearly unlimited opportunity to misrepresent
the real results. This deficiency was compounded by the policy that major
projects could overrun by tens of millions of dollars without board
oversight, due to there being no cap on the 10% overrun allowance.
The Consequences
Why
is the lack of a policy requiring board approval of deductive changes
costly?
-
As is oft said, the tone begins at the top. When the senior executives use
this dodge, their behavior is seen all the way down to the project manager
level. Project management may further obscure project results in ways not
revealed to senior management. The deception feeds upon itself, magnifying
the undesirable consequences.
-
With this loose standard, unworthy projects can be misrepresented to
garner board approval.
-
The lack of a deductive appropriation change requirement allows funds to
be shifted to purposes not authorized by the Board of Directors. This
sometimes extends to fraud.
-
This process renders project cost evaluation nearly impossible,
particularly in comparison to other projects or planning for future
projects.
-
Management performance in managing capital projects is irreparably
obfuscated at all levels.
-
A frequent casualty is increased capacity intended to serve future
expansions. The cheaper alternative of reduced scope is adopted.
Therefore, subsequent projects may be far more expensive to complete.
Boards only learn that this has happened when the next level of expansion
follows closely on the heels of the one just completed.
What is lost when the organization allows 10 to 15% overruns without Board
approval on large projects (and some senior management approval on small
ones)?
-
Cost overruns become accepted as the norm, with under-spent projects being
unheard of.
-
Projects stay open until they are overspent by the allowed percentage.
-
Coupled with the lack of deductive change approvals, above, adoption of
allowable overrun percentage permits enormous cost overruns with no
scrutiny.
Moving Forward
It
is not mandatory that the Board of Directors approve ALL deductive changes
to achieve good controls. An exceptional set of controls takes into
consideration Board oversight limitations and the corporate culture in
establishing at what level of management deductive changes must be approved.
This should extend throughout the project cycle and down to the level of
construction field changes.
A
comprehensive set of scope controls substantially reduces the opportunities
for fraud and puts tools in place to more readily detect fraud.
With scarce capital project funding in the current business environment and
single-digit increases in earnings forecast in nearly every industry for the
next decade, can corporations and other organizations really afford such
loose capital spending processes? If they do not improve, will their
competitors be so lax?
Scope control is critical to successful prosecution of capital projects.
Recognizing the Scope Deletion Dodge and its ultimate effects is only a
starting point. Starting at the top is usually productive. Once the board
and senior management are persuaded, their commitment and example quickly
transform the culture to one that preserves capital instead of squandering
it.
Then everyone can take pride in knowing that a project completed “on time
and under budget” truly was a success, not some accounting fiction.
The author, Al M. Gray, is the founder and
Company President of Capital
Project Review Services, Inc. (CPRS), a Georgia corporation that offers
proactive project auditing and controls methods geared to reduce project
costs, project tax accounting programs designed to minimize state sales and
use taxes, and cost recovery reviews for projects which are underway or have
been completed. Email address
Cprsi@mindspring.com |